CLIENT: Aquarius Platinum

PROJECT: Everest
REGION: South Africa
STATUS: Completed

SCOPE OF WORKS

Development of the mine through the simultaneous sinking of 5 declines plus a vertical ventilation shaft.

Trackless production mining planned at 200 000 tonnes per month

SPECIAL ACHIEVEMENTS AND CHALLENGES

The layout of conveyors and feeders to remove rock was very well planned and installed.

Sinking of 5 declines in very close proximity to each other provided logistical and coordination challenges that were well managed.

Contact Us